January update from Cala Homes

  • The first 4 plots are now ready for internal drainage and beams
  • 50% of the site roads are now tarmacked, which should help greatly in keeping the main highways clean
  • Pile mats are now complete ready for the piling rig to come in on the W/c 07/01/19, to take around 2 weeks
  • Stable is now demolished
  • The rest of the internal roads to start W/c 07/01/19 to be completed by the end of January
  • Surface water storage crates system to be installed around 10/01/19
  • Water mains to be installed W/c 21/01/19
  • Gas mains to be installed W/c 28/01/19
  • Work on the site office and compound to start the end of January